Thirty men take 20 days to complete a job working for 9hrs a day, how

MATHEMATICS
POST UTME UNILORIN

Thirty men take 20 days to complete a job working for 9hrs a day, how many hr(s) a day should 40 men to work to complete the job?

  • (a) 8
  • (b) 7.5
  • (c) 7
  • (d) 9

Correct Answer: (b) 7.5