Nasara Manufacturing Plc has three direct labour employees that work 40 hours each a week for 50 weeks a year. Factory overhead costs of N60,000 is distributed on the basis of direct labour hours. Compute the overhead rate?
- A. N12 per hour
- B. N16 per hour
- C. N10 per hour
- D. N15 per hour
Correct Answer: C. N10 per hour