Given: N Direct material - 10 000 Direct labour - 5000 Direct expenses - 2000 Factory overhead - 4000 What is the prime cost?

  • A. N21 000
  • B. N 17 000
  • C. N 15 000
  • D. N 6 000

Correct Answer: B. N 17 000